Bill of quantities breakdown structures BQBS
Contents |
[edit] Introduction
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor) that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers for them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are three main breakdown structures for bill of quantities (BQBS), each with advantages and disadvantages. If preparation of the bill of quantities is digitised according to a standard codification, it may be possible to re-order it from one structure to another.
[edit] Elemental
Measurement and description is undertaken by group elements, with each group element forming a separate section of the bill of quantities, irrespective of the order of work sections in NRM 2. Group elements are sub-divided through the use of elements, which are further sub-divided by sub-elements, as defined by NRM 1: Order of cost estimating and cost planning for capital building works.
This structure can make it easier for the cost consultant to analyse contractors' tender prices and collect real-time cost data.
For more information see: Elemental bill of quantities.
[edit] Work section
Measurement and description is divided into the work sections listed in NRM 2.
This structure may be preferred by contractors, as similar products and components are grouped together, rather than being spread across a number of different elements as they are in an elemental breakdown. This can make pricing easier for contractors.
For more information see: Work section bill of quantities.
[edit] Work package
Measurement and description is divided into employer, quantity surveyor or contractor defined work packages (based either on a specific-trade, or a single package comprising a number of different trades). This structure may be preferred by contractors for procuring from their supply chain.
For more information see: Work package bill of quantities.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Product breakdown structure.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Uniclass.
- Work breakdown structure.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.